BHS Project Moving Ahead Slowly

June report says prep of staging area north of Patterson Way has begun. Abatement work scheduled to start end of summer 2012 but that seems unlikely.

 

Berlin High School Renovations Report

  • Activities Since Last Month – Design & Field Progress Overview:
  • Silver Petrucelli returned to the State on Thursday, June 21st with revisions to the documents based on the local review. The only remaining open item is final EPA approval.
  • Expecting final release from the EPA on abatement plans for PCB containing caulk within two weeks.
  • The State Traffic Commission approval letter was received on June 21, 2012 and forwarded to the State and the town. The town has filed the letter on the land records.
  • The design team is has continued progress on the Design Development documents.
  • 75 percent Design Development Documents were provided to the ConstructionManager, independent estimator, Board of Education, and Public Building Commission on June 25th.
  • Proposed phasing plans were presented to the Board of Education on Monday, June 25th.

30 Day Look Ahead:

Find out what's happening in Berlinwith free, real-time updates from Patch.

  • Silver Petrucelli anticipates State approval of plans by mid-July.
  • FIP will publicly advertise for bids for the Phase 1 – Abatement and Pre-engineered Building.
  • Silver Petrucelli will have Design Development documents complete by the 3rd week of July.
  • Estimates are anticipated to be ready to reconcile at the same time. Presentation to the Public
  • Building Commission and the Board of Education will follow.
  • Continue design meetings on High Performance Building Design options with Berlin DPW, the
  • Commissioning Agent, and the Design Team.
  • Work to prep the staging area north of Patterson Way began on June 29th and should be complete within 3 weeks.

Critical Issues:

  • Final approval of Phase 1 documents by the State for bidding.
  • Completion of Design Development Documents and estimate.

Budget:

Find out what's happening in Berlinwith free, real-time updates from Patch.

  • Referendum Approved Budget: $69,950,000

Schedule:

  • Phase 1 – Abatement and Pre-Engineered Building Wing.
  • Anticipated Start: Summer/Fall 2012
  • Phase 2 – Structural, Architectural, MEP, and Technology:
  • Anticipated Start: Early 2013